A complete RFQ template for steel pipe procurement. Six essential specifications procurement officers need to include for fast, accurate quotations.
For a Kanpur order, send the six technical lines before requesting ex-warehouse or delivered pricing. A complete steel-pipe RFQ contains six controlled specifications: process, governing standard and grade or class, outer diameter or nominal size, approved wall or schedule basis, length basis, and quantity in MT or metres. Add coating, end finish, the approved inspection-certificate type, and any component-specific IBR or TPI requirement as separate lines. Ask the supplier to state its response date and list every assumption or deviation.
A Kanpur RFQ should identify the pipe, the inspection basis, and the delivery point before a supplier prices the order. The six technical lines remain the core. Add the destination PIN code, ex-warehouse Kanpur or delivered basis, GST treatment, and the documents required with dispatch. That structure lets buyers compare material and freight on the same basis.
For an RP Sales enquiry, ask the quotation to confirm the actual Kanpur dispatch point and whether the material is identified there, held upstream, or requires mill production. A local fabricator may request collection. A PWD or JJM contractor may need delivery to a project site. Sugar mills and hydraulic or printing-cylinder shops may ask for phased dispatch against production schedules.
Treat the RFQ as a controlled specification, not an informal product enquiry. The supplier should be able to copy each requirement into the quotation and later into the PO. If a line remains open, label it for supplier confirmation. A blank line can otherwise turn into an assumption about class, length, coating, inspection, or freight.
Procurement teams can use this template for repeat stock purchases, tender enquiries, maintenance orders, and fabrication inputs. It fits IS 1239 ERW or GI requirements, seamless boiler-tube enquiries, precision hydraulic tube, and borewell casing. The buyer still needs the project engineer to choose the governing standard and service conditions.
A purchaser should not use the template to select a pressure rating, temperature limit, corrosion allowance, or material grade without engineering approval. Those decisions belong in the design documents. The RFQ transfers the approved requirement to suppliers and requests a commercial response. It does not replace a piping class, tender specification, drawing, or approved vendor requirement.
PWD and JJM bidders should copy the accepted BOQ description and inspection requirements without shortening the standard designation. Fire-system installers should retain the approved pipe class and end connection. Sugar-mill maintenance teams should identify any IBR documentation requirement. Hydraulic and printing-cylinder shops should state OD, ID or wall, finish, straightness, and cutting needs.
Line 1 — Process: State the approved method of manufacture and governing standard together. Do not infer the process from a standard family: for example, IS 3589 covers seamless, ERW, and SAW pipe, while individual ASME material specifications have their own scope. Copy the designation from the drawing, piping class, tender, or engineer-approved material list.
Line 2 — Grade: Use the explicit grade or class designation from the governing specification, such as IS 1239 medium class, SA210 Grade A1, or ASTM A53 Grade B where the project actually calls for it. Avoid vague terms such as standard or regular. The supplier should quote the exact designation offered and identify any deviation.
Line 3 — Outer diameter: State in mm (and NB/inches if known). Example: "168.3 mm OD (6" NB)". Include tolerance requirement if tight-fit assembly.
Line 4 — Wall thickness: State the approved wall in mm, class, or schedule together with its dimensional standard. For an IS 1239 order, copy the approved light, medium, or heavy class. Wall is only one input to pressure design; outside diameter, material strength, temperature, allowances, joint efficiency, and the governing design code also matter.
Line 5 — Length: State fixed length, a clearly defined random-length range, or cut-to-length. Write the permitted range and tolerance in the RFQ instead of assuming that SRL or DRL has the same numeric meaning across every supplier and specification.
Line 6 — Quantity: In metres or MT. Declare delivery instalments if phased. For a proposed mill-direct order, ask the named source to quote any MOQ and quantity tolerance; see the MOQ planning page.
End finish determines site weldability: plain end (weld-ready), beveled (for butt welding), or threaded & coupled (T&C). The fitter cannot weld a T&C end without re-cutting — specify up front.
Coating changes the product and commercial scope: black or as-rolled, hot-dip galvanized where the applicable product specification and IS 4736 are invoked, or a separately approved epoxy or 3LPE system. State the required coating standard, preparation, inspection, repair, and acceptance criteria; ask the quotation to price that scope separately.
State the inspection document required by the project rather than assuming EN 10204 type 3.1 or 3.2 is universal. If a 3.2 document, TPI witnessing, or an IBR certificate is required, identify who validates it and the hold point before manufacture or dispatch.
Documentation bundle: e-way bill, GST invoice, packing list, MTC, TPI report, IBR certificate. Confirm required docs to avoid dispatch delays.
Yes — our RFQ form prompts for each of the six lines plus secondary specs. The form validates input and routes directly to the quoting desk. Use the button below to open a prefilled RFQ with "Steel pipe procurement" as the subject.
List each document as a deliverable rather than writing a broad phrase such as complete quality papers. Ask for the mill MTC, invoice, packing list, e-way bill where applicable, and weighbridge evidence. For IBR work, copy the component-specific certificate requirement from the approved design or inspecting authority: Form III-A covers pipes or steam piping, Form III-B covers tubes, and Form III-C covers boiler mountings and fittings. The quotation should confirm which party arranges TPI.
Tie the MTC to heat or batch markings on the material. Ask the supplier to show the same grade, size, process, and standard across the quotation, MTC, packing list, and invoice. A document set with conflicting descriptions needs correction before dispatch. Procurement staff should also state whether scanned copies are needed before the vehicle leaves Kanpur.
Specify the inspection point. Buyers may inspect at the Kanpur yard, nominate a third party, or inspect at receipt. A tender may require a hold point before loading. State the notice needed for inspection without assuming the supplier can arrange an inspector after the vehicle arrives. Keep acceptance terms and the remedy for non-conforming material in the PO.
Packing instructions should match the unloading plan. State bundle identification, end protection, and any separation by size or heat. A mixed truck can save freight, but the receiver must distinguish each line item. Ask for a bundle-wise packing list when several sizes travel together to Lucknow, Agra, Prayagraj, Varanasi, Gorakhpur, Jhansi, Bareilly, or Patna.
Assume a buyer needs an approved IS 1239 (Part 1) ERW line in medium class. A controlled RFQ line can read: 80 NB, 6 m fixed lengths, 120 lengths, plain ends, black finish, mill MTC required. The quantity is 720 m by count. If the drawing controls a particular wall or dimensional tolerance, copy that requirement into the same line rather than asking the supplier to infer it from the nominal bore.
Ask the supplier to return the offered standard, class, process, length count, commercial weight basis, mill source, MTC status, and any deviation beside that line. This lets procurement compare the offered material with the approved requirement before converting the quotation into a PO. It also gives stores a length count and document expectation for receiving.
The RFQ should also state inspection point and delivery basis. A Kanpur pickup quote should say ex-warehouse Kanpur. A delivered quote should name the project PIN code, freight responsibility, and unloading responsibility. Ask the supplier to show the applicable GST rate and product-specific HSN separately; do not assume one pipe heading covers every seamless and welded product.
Build the comparison sheet from the RFQ lines. Start with standard, grade, process, OD or NB, wall or class, length, and quantity. Then compare coating, end finish, mill source, MTC, inspection, packing, delivery basis, GST, payment terms, validity, and dispatch commitment. Mark deviations beside the affected line instead of hiding them in notes.
Separate the material rate from applicable GST and freight. The site price lists quote ex-warehouse Kanpur bands with tax shown as an extra line. A delivered offer may look higher while carrying the transport cost that another quotation excludes. Ask the supplier to state the product-specific HSN and restate any combined figure before selecting the lowest evaluated offer.
Check unit consistency before comparing totals. One supplier may quote per kg, another per MT, and another per length. Convert each against the same theoretical or commercial weight basis. Keep the supplier value visible beside the converted value. That record helps the accounts team reconcile the invoice and helps the site team verify the received bundle.
Read exclusions with the same care as the rate. A low quotation may exclude threading, coating, testing, unloading, TPI, or required documents. Record the commercial consequence of each exclusion. Procurement should seek clarification before issuing the PO, since a post-order change can affect availability and dispatch planning.
| Control | Buyer entry | Supplier entry | Review basis |
|---|---|---|---|
| Pipe identity | Standard, grade, process | Offered designation | Exact match or approved deviation |
| Dimensions | NB or OD; wall or class | Quoted dimensions | Approved drawing or BOQ |
| Quantity | Lengths, metres, or MT | Commercial weight basis | One common comparison unit |
| Documents | MTC, IBR, or TPI scope | Included document set | PO acceptance requirements |
| Delivery | Ex-warehouse Kanpur or PIN code | Freight and unloading basis | Comparable landed obligation |
Using only NB without class or wall leaves the supplier unable to choose the correct pipe. Naming a schedule without the governing dimensional standard creates the same problem. Write the complete designation from the drawing or BOQ, then ask the supplier to state any offered deviation in the quotation.
Combining several destinations under one undivided quantity obscures freight and packing. Split the enquiry by delivery PIN code and required date. The supplier can still consolidate material at the Kanpur yard, but each destination receives a clear packing list and freight line. This matters for tender packages spread across several sites.
Requesting MTC or IBR papers after dispatch can leave procurement without the required document path. Put each certificate and inspection hold point in the RFQ and PO. Ask for heat traceability before cutting or mixing bundles. Cut-to-length material needs its identification plan agreed before processing starts.
Sending photographs or old invoices without a written specification makes the supplier infer critical details. Use those attachments as supporting evidence only. The RFQ text should control the order. If a drawing conflicts with the written line, ask the engineer to resolve the conflict before suppliers price it.
Leaving delivery basis unstated prevents a fair comparison. Use a precisely defined Kanpur handover for buyer pickup or name the delivered site. Add loading and unloading responsibility, vehicle restrictions, receiving hours, and the required date. The supplier should then return its actual dispatch point and commitment.
Copy and paste this template into your procurement system or email. Fill in the bracketed fields and send to suppliers for faster, more accurate quotations.
**TO:** Steel Pipe Supplier **FROM:** [Buyer legal name] **DATE:** [Date] **REF:** RFQ-[Number] --- **1. PROCESS:** [ ] ERW [ ] Seamless **2. STANDARD / GRADE OR CLASS:** _______________________ (e.g., required IS 1239 grade + medium class / SA210 Gr A1 / ASTM A53 Gr B) **3. OUTER DIAMETER:** _______ mm (NB: _______) **4. WALL THICKNESS:** _______ mm / Schedule _______ **5. LENGTH:** [ ] Fixed: _______ m [ ] Random range: _______ to _______ m [ ] Cut-to-length: _______ m **6. QUANTITY:** _______ MT / _______ metres **7. END FINISH:** [ ] Plain [ ] Beveled [ ] Threaded & Coupled **8. COATING:** [ ] Black [ ] Hot-dip galvanized [ ] Epoxy [ ] 3LPE **9. INSPECTION DOCUMENT:** Approved type/reference: _______________________ **10. IBR/TPI:** Component-specific IBR certificate (if applicable): _______ TPI by: _______ **11. DELIVERY:** - PIN Code: _______ - Site address: _______________________ - Instalments: _______ **12. TARGET DELIVERY:** _______ **13. SPECIAL NOTES:** _______________________ --- Please quote: - Unit rate per MT (₹) - Applicable GST rate and product HSN (included/extra) - Delivery basis and named handover place - Lead time (days) - Payment terms - Quote validity (days)Open Prefilled RFQ Form
| RFQ response date | Supplier to state in the quotation |
|---|---|
| RFQ assumptions | Supplier to list every open item and deviation |
| Quote validity | Dated validity to be stated by supplier |
| Availability basis | Identify yard stock, upstream stock, or mill production |
| Document timing | Agree the pre-dispatch review and release hold point |
Share the grade, dimensions, quantity, delivery location, and documentation needs so the requirement can be reviewed before pricing and availability are confirmed.