
Dispute & Return Handling — What Good Suppliers Offer in Writing
Steel pipe dispute resolution and return policies. Written guarantees procurement officers should demand before placing orders.
Good steel pipe suppliers document their dispute handling before the PO is signed: non-conformance claims accepted within 7 days of dispatch with photo evidence and MTC reference; short shipments replaced at supplier cost within 48 hours of verification; wrong grade dispatched triggers immediate replacement with correct material or full credit note. Get these terms in the PO termsheet — verbal promises evaporate when 20 MT of wrong-grade pipe arrives at your site with project deadlines looming.
What should a written return policy include?
Claim window: Specify days from dispatch (not delivery — transit is supplier's risk if freight-included). Standard is 7 days for visual/dimensional defects; 48 hours for short shipment count disputes.
Evidence required: Photos of damage/defect with pipe markings visible; copy of MTC; packing list; waybill. This links the problem to the specific dispatch batch.
Resolution options: Replacement at supplier cost (best), credit note against future purchases (acceptable for minor issues), or refund (rare — steel is not typically returned, only replaced).
Exclusions: Cut-to-length orders (cannot be resold), willfully damaged material, and pipes installed/welded (acceptance upon installation). State these clearly to avoid dispute.
How do legitimate suppliers handle non-conformance?
Dimensional non-conformance (OD/wall thickness out of spec): Return freight paid by supplier; replacement dispatched within 5 days of claim acceptance.
Wrong grade dispatched: Immediate replacement with correct grade; supplier arranges reverse logistics for wrong material. If correct grade unavailable, full credit note issued.
Short shipment: Verified against packing list and waybill. Missing quantity reissued at supplier cost within 48 hours; expedited transport if project-critical.
Documentation errors (wrong MTC, missing IBR): Corrected documents couriered within 24 hours; IBR correction requires mill re-issuance (5-10 days).
What protections should my PO include?
Material acceptance clause: "Material subject to inspection and approval. Payment does not constitute acceptance."
Liquidated damages: For late delivery beyond agreed date, 0.5-1% of order value per week of delay, capped at 5-10% of total.
Force majeure: Defined exclusions (natural disasters, mill strikes, government shutdown). COVID-19 is no longer force majeure; supplier should have adapted.
Governing law: Indian Contract Act, 1872; jurisdiction of Kanpur courts or mutually agreed arbitration (ICA rules).
Termination for convenience: Buyer right to cancel unshipped portion with 7 days notice and full refund of advance.
Dispute scenarios and standard resolutions
| Scenario | Evidence needed | Standard resolution | Timeframe |
|---|---|---|---|
| Dimensional out-of-spec | Photos + MTC + caliper readings | Replacement at supplier cost | 5 days from claim |
| Wrong grade dispatched | Photos of pipe markings + MTC | Replacement or credit note | 7 days from claim |
| Short shipment | Packing list + waybill + unloading photos | Reissue missing quantity | 48 hours from verification |
| Visible surface defects | Photos pre-installation | Replacement or credit (partial) | 5 days from claim |
| Missing documentation | Packing list comparison | Courier corrected docs | 24 hours (MTC), 5-10 days (IBR) |
| Late delivery | Waybill date vs PO date | Liquidated damages per PO terms | NA — claim against LD clause |
Specifications at a glance
| Standard claim window | 7 days from dispatch |
|---|---|
| Short shipment claim window | 48 hours from receipt |
| Replacement dispatch time | 5 days from claim acceptance |
| Credit note processing | 14 days from claim acceptance |
| Liquidated damages rate | 0.5-1% per week (cap 5-10%) |
| Non-returnable categories | Cut-to-length, installed, willfully damaged |
Related pages
Frequently asked questions
Can I return steel pipes if I ordered the wrong size?
What if the supplier refuses to accept my claim?
Do I pay freight on replacement shipments?
How do I prove non-conformance?
What is "acceptance upon installation"?
Need Steel Pipes in Bulk?
Get a same-day quotation with competitive pricing. We supply across UP, Bihar, MP & Delhi NCR.